Russell First requested an update on the permitting process from Russell Biomass.  The table below shows the numerous permits that the company has applied for, received (highlighted in green), or is awaiting.  Russell Biomass has said that by early 2010 it expects to receive all permits and regulatory decisions necessary to enter construction.  However, Russell Biomass also said that it expects some permits will be appealed by project opponents. 

 

 PermitRegulatory Agency
Permits Required Prior to Construction Financing
1Major Comprehensive Plan ApprovalGeneration Facility – Air and NoiseMassachusetts Department of Environmental Protection (MADEP)
2Environmental Impact Review Generation Facility and Transmission FacilitiesMassachusetts Environmental Policy Act (MEPA)
3Special Permit Generation FacilityTown of Russell Zoning Board of Appeals/ Planning Board 
4Water Management Act (WMA)Generation Facility l MADEP
5Chapter 91 - Request for Determination of ApplicabilityGeneration Facility MADEP
6National Pollution Discharge Elimination System (NPDES) Individual PermitGeneration Facility MADEP/ United States Environmental Protection Agency (USEPA)
7Request for Interconnection for a Large Generating FacilityTransmission FacilitiesIndependent System  Operator – New England (ISO-NE)
8Petition for Approval of Construction/ Section 72 Petition/ Petition for Zoning Exemption Transmission Facilities Energy Facility Siting Board (EFSB)
9Petition for Zoning Exemption Generation Facility Dept. of Public Utilities (DPU)
10Authorization to AccessTransmission FacilitiesMassachusetts Turnpike Authority
11Water Quality Certification Section 401 Clean Water ActGeneration Facility and Transmission Facilities and Frog Hollow Road Extension (FHX) MADEP
12Programmatic General Permit/Individual Permit Section 404 Clean Water ActGeneration Facility and Transmission Facilities and FHXArmy Corps of Engineers (ACOE)
13Orders of Resource Area DelineationGeneration Facility and Transmission FacilitiesRussell, Montgomery, Westfield Conservation Commissions and MADEP
14AOrders of ConditionsGeneration Facility  Russell Conservation Commission and MADEP
14BOrders of ConditionsTransmission Facilities Russell Conservation Commission and MADEP
14COrders of ConditionsFHXRussell Conservation Commission and MADEP
15Orders of ConditionsTransmission FacilitiesWestfield Conservation Commission and MADEP
16ADetermination of No Adverse Impact / TakeGeneration Facility and Transmission FacilitiesNHESP/Massachusetts Division of Fisheries and Wildlife (DFW)
16BDetermination of No Adverse Impact / Takeincluding FHXNHESP/Massachusetts Division of Fisheries and Wildlife (DFW)
17Conservation and Management PermitGeneration Facility and Transmission Facilities and FHXNHESP/DFW
18Permit to Access State Highway at Main Street/Route 20 Generation Facility and FHXMassachusetts Highway Department
19Determination of No Adverse ImpactGeneration Facility and Transmission Facilities and FHXMHC
20Article 97Transmission FacilitiesMA Legislature
21Russell Special Permit - AmendmentGeneration Facility to include FHX as accessRussell Zoning Board of Appeals
22Russell Site Plan ReviewGeneration Facility to include FHX as access Russell Planning Board
23Russell Special Permit for Earth Removal Generation Facility Russell Zoning Board of Appeals
24Russell Site Plan ReviewTransmission FacilitiesRussell Planning Board
25Russell Special Permit for Earth RemovalTransmission FacilitiesRussell Zoning Board of Appeals
26Westfield Zoning PermitTransmission FacilitiesZoning Enforcement Officer
27Westfield Building/Structure Height and Stormwater Management Special PermitTransmission FacilitiesWestfield Planning Board
   
 


 

 
 PermitRegulatory Agency

 

Permits to be Submitted Post Construction Financing and Design
28NPDES Notice of Intent (NOI) to be covered under the General Permit for Stormwater Discharges from Construction Activities, Storm Water Pollution Prevention Plan (SWPPP)Generation Facility and Transmission Facilities USEPA

 

29Subsurface Sewage Disposal Works PermitsGeneration Facility and Transmission Facilities Russell and Westfield Boards of Health

 

30Stack RegistrationGeneration FacilityFederal Aviation Administration (FAA)

 

31Transmission Line Structure RegistrationTransmission FacilitiesFederal Aviation Administration (FAA)

 

32Fuel Oil Tank Permits (requires final design)Generation Facility State Fire Marshal/Local Fire Department

 

33Use Permit Under 502 (requires final design)Generation FacilityState Fire Marshal/Local Fire Department for ammonia and fuel oil storage tanks

 

34Permit for Construction Related Activities and Traffic ManagementTransmission FacilitiesMassachusetts Turnpike Authority

 

35Building PermitsGeneration Facility, Transmission Facilities and FHXRussell, Montgomery, Westfield Building Inspectors State Building Code

 

36Beneficial Use Determination (BUD) (ash reuse)Generation FacilityMADEP

 

     
   

 